Dear Members,
We wish to inform members that the Johore Bar Committee attended a stakeholder engagement session organised by the Johor State Court on 19 November 2026 concerning the relocation of the Johor Bahru Courts to the new court complex at Kota Iskandar, Iskandar Puteri.
The session was attended by representatives of various agencies and stakeholders. The Court provided an update on the relocation arrangements and conducted a walkthrough of the new complex.
We set out below the salient matters arising from the meeting for members’ information.
1. Commencement of Operations and Relocation Schedule
The new court complex is scheduled to commence operations on 1 January 2027.
The relocation arrangements are as follows:
- 16–30 November 2026: Administrative preparations, including file registration.
- From 1 December 2026: Commencement of the transfer of court files, assets and equipment to the new complex.
- Until 31 December 2026: All hearings and court proceedings will continue at the existing Johor Bahru Court Complex.
- 1 January 2027: Scheduled commencement of operations at the new complex.
Members are advised that court proceedings will continue at the existing premises throughout December 2026, notwithstanding the ongoing relocation exercise.
The Court has indicated that measures will be taken to minimise disruption, although some administrative inconvenience may arise during the transition.
2. Location of Courts at the New Complex
The new court complex comprises two principal blocks, with the following arrangements:
Block A – High Court
- Level 2: High Court (Civil)
- Level 3: High Court (Criminal)
- Level 3: Mahkamah Khas, which will accommodate Sessions Court (Civil 1)
Block B – Subordinate Courts
- Sessions Courts (Criminal & Civil)
- Magistrates’ Courts (Criminal & Civil)
- Mediation Centre
- Court registries and counters
- Library and other administrative facilities
Members should note that certain Sessions Courts will be renumbered as part of the relocation exercise. In particular, the existing Sessions Court (Civil 6) is expected to be redesignated as Sessions Court (Civil 1).
Other proposed changes, including the renumbering of certain criminal courts, remain subject to official confirmation.
The Court is expected to provide further details on the final allocation and numbering of courtrooms.
3. Parking Facilities
Parking availability was among the concerns raised during the engagement session.
The Court informed stakeholders that approximately 55 to 60 public parking spaces are presently available at the new complex.
The Johore Bar Committee raised concerns regarding the adequacy of parking facilities, particularly having regard to the number of advocates and solicitors, litigants and members of the public attending court daily.
We were informed that discussions are ongoing with the local council (MBIP) concerning the possibility of additional roadside parking.
At present, parking is expected to operate on a first-come, first-served basis. No dedicated parking arrangement for advocates and solicitors has been confirmed.
The Committee will continue to raise this matter with the Court.
4. Other Facilities
The following facilities and arrangements were also discussed:
- Mediation Centre: A centralised mediation facility is intended to serve the High Court and Subordinate Courts.
- Cafeteria: A designated cafeteria space is available. The Court is exploring the appointment of an operator.
- ATMs and Cash Deposit Machine (CDM): The existing machine is expected to be relocated to the new complex.
- Agency and Interview Rooms: Designated rooms have been allocated for relevant agencies, including legal aid and welfare-related functions, subject to space limitations.
5. Further Updates
The Court has indicated that further information concerning operational arrangements will be communicated as the relocation progresses.
The Johore Bar Committee will continue to engage with the Court, particularly on matters affecting members’ daily practice, including parking, courtroom allocation, registry services and access to court facilities.
Members will be informed of further developments upon receipt of official confirmation.
We thank members for their attention and cooperation during this transition.